Order Standard Costs Based on Material Cannot be Calculated

former_member660347
Discoverer
0 Kudos

Hi,

In attempting to complete the Create Production Order step of the Production Planning process, I encounter an error message that says "Error calculating costs, see log". When I check the log, it reads "Order standard costs based on material cannot be calculated". I have standard values for labor entered into each step of the routing.

When I create a material cost estimate with quantity structure through CK11N, all raw materials are costed but the labor activity is not.

Is there something that I'm missing in the creation of the BOM, Routing, or Material Master that could be causing this issue? Could it be something else in the Work Center or Cost Center?

Thank you,

Adam

costing-issue-1.png

costing-issue-2.png

costing-issue-3.png

View Entire Topic
100087063322
Explorer
0 Kudos

Please check the "Start" date and "End" date of the order. If the the standard cost is not released within this date, the message "Order Standard costs based on material XXXX cannot be calculated." will come.

For example if the cost is released from 04.04.2024 to 30.04.2024

100087063322_0-1713157284719.png

and the order start date is 30.05.2024-  The message will pop up.