Order Standard Costs Based on Material Cannot be Calculated

former_member660347
Discoverer
0 Kudos

Hi,

In attempting to complete the Create Production Order step of the Production Planning process, I encounter an error message that says "Error calculating costs, see log". When I check the log, it reads "Order standard costs based on material cannot be calculated". I have standard values for labor entered into each step of the routing.

When I create a material cost estimate with quantity structure through CK11N, all raw materials are costed but the labor activity is not.

Is there something that I'm missing in the creation of the BOM, Routing, or Material Master that could be causing this issue? Could it be something else in the Work Center or Cost Center?

Thank you,

Adam

costing-issue-1.png

costing-issue-2.png

costing-issue-3.png

View Entire Topic
former_member198692
Active Contributor
0 Kudos

Hi Adam,

Check Control key assigned in routing it should have cost ticked in OPJ8

for your reference.

OPJ8

Regards,

Prasad