on 2011 May 26 1:42 PM
Dear Masters,
I am facing a problem in release an order which is created through a maintenance plan.
I am getting error "No task list selected" with message as "Message no. IW322" please explain me what this message mean to say, because I have already attached task list to my order and operations from task list are already extended to my order operation.
Why am I getting this message? Is there any configurational change to made in the order type?
All the other order types are working properly Only this order type is showing me the error.
Thanks in advance
Request clarification before answering.
Check the date of creating TASK list and compare with Order Basic Start date.
Should the same or Order start date greater than task list created date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
112 | |
9 | |
6 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.