Hi,

In CM01 does it display till 6 months only, Since I am changing number of days to more than 180 in OPA3 fro option profile but it is always showing till 180 days only and in past it is going to 30 days, is this standard SAP or is it possible to display more than 180 days? Suggest me,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Create the selection profile and specify the period (OPA2).

Create the option profile and specify the period (OPA3).

Create the overall profile to link selection and option profile together (OPA6).

In CM01, you can change the overall profile in menu path Planning -> Profile -> Overall profile.

You can default the overall profile in user parameter CY1.

Former Member
0 Kudos

Hi,

I have done specified process earlier but does it really display morethan 180 days as it is allowing 365 days in OPA3 but always it is showing 180 days only. samething when I checked by changing to calendar weeks with 52 but still it is showing for 6 month sonly. does this standard or am I doing any mistake? Please advise me.