on 2010 Mar 31 5:09 PM
Hi
Iam using parallel sequence with branch operation 0 and return operation as 40 return operation.
There are 15 operations in main sequence
I have created 3 production orders each with quantity 1, for same material with same finish date.
For parallel sequence, last operation date comes different in 2 production orders and different in one operation.
When 2 production orders are re-schedule then in all production orders dates for parallel sequences come properly.
Please guide why dates in all 3 production orders are not coming same during creation mode.
Dear,
Check the alignment key you want, either specify earliest start or end, depending on how you want to schedule them in your parallel sequence on that basis if we select the backward or forward scheduling date changes.
Pl. refer this link
http://help.sap.com/erp2005_ehp_04/helpdata/en/7e/d42611455911d189400000e8323c4f/frameset.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.