Operation Overlapping in Production order- PP

Suryansh_jain
Explorer
0 Kudos
179

 

My order qty is 100 PC with required overlapping, min overlap time as 2 HR, min send ahead qty 1. Still second operation is not overlapping with 1st operation. 2nd operation starts only after the 1st is completed.

Any idea why overlapping is not happening?

 

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You have defined a minimum overlap time of 2 hours, so you need to ensure you have operations long enough to overlap. 

Regards,
Caetano 

Suryansh_jain
Explorer
0 Kudos
Hi Caetano, Thanks for your response. You mean 2nd operation should have long enough time to overlap?
Suryansh_jain
Explorer
0 Kudos
Still overlapping not happing..any other data required to maintain?