on 2012 Apr 18 4:18 AM
Hi:
I am testing OCM process for sales order..But no change at all when I execute COCM,I didn't see any change object there..It's empty..
1.Create Sales order
2.MD50 run MRP for this sales order and convert it to production order,then release it
3.Change the sales order(change description and order priority)
4.COCM but no change object displayed...
what's wrong with it?am I wrong when change the sales order?thanks very much..
Request clarification before answering.
Hi,
Where are you expecting this change in sale order description to be adopt by OCM?