Dear Experts,

My User facing the below error message: I have gone through the scn post but I am not able to resolve this issue kindly suggest me.

No price could be determined for material/batch 3000000714/ plant 1020

Message no. CK465

Diagnosis

The system could not calculate a price for material/batch 3000000714/ in plant 1020 for valuation view 0, because none of the valuation strategies in valuation variant 007 was successful.

System Response

User-defined error management enables you to specify whether the message is an error message, a warning message or an information message.

  • If you have defined the message as a warning message or an information message, the costing item will be entered in the cost estimate with a value of zero.
  • If you have defined the message as an error message, the cost estimate contains an error or errors.

  • If the system issues a termination message, the cost estimate cannot be processed, and processing is terminated.

Procedure

  • Check the master data for material/batch 3000000714/ in plant 1020.

  • If you have authorization for Customizing, check the valuation strategy for materials in valuation variant 007.

Note

If the message is a warning message or an information message, there is a danger that materials with errors will be ignored by the system.

If, because of this, you issue a warning message and at the same time include materials with a zero value in cost estimates, you can make the following settings for these materials in the costing view of the material master:

      1. Enter a very low price in the

planned price 1

      ,

2

      or

3

    fields manually, for instance 0.01 USD. These prices are used for costing purposes only; they are not read by other applications.
      2. Enter the highest price unit possible, for example 10000.

    Note: If you enter a new price unit that is higher than the costing lot size, the system increases the costing lot size accordingly.
    3. Change the valuation strategy, such as strategy 4, where you could enter the planned price field in which you entered the low price.

    The system now costs as follows:
    Using the valuation strategy, the system finds planned price 1, 2 or 3. Due to the low price and high price unit, the system rounds the value to zero. However, the cost estimate still obtains status KA (free of errors), and no error message is issued.

  • This procedure can be used for all materials that have caused error message CK465 to be issued.

Regards,

Ramesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member197165
Participant
0 Kudos

Dear Amol/Maria,

I have maintained the material price by t-code MR21 and then calculate the cost in order again no error is occured.

is this solution correct please let me know.

Regards,

Ramesh

MTerence
Active Contributor
0 Kudos

Good, Check whether the plan cost is calculated and post the actual. If both places you get cost, then you have fixed the issue.

Regards

Terence

Former Member
0 Kudos

yes.

Regards,

Amol

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Ramesh,

System is not able to find valuation view in method, GET_VALUATION_VIEW. I think as suggested bu Maria, please contact MM person for assistance.

Regards,

Amol

former_member197165
Participant
0 Kudos

Hello Maria,

There is no valuation category is defined for this Material and material type ERSA. I have created simple order for maintenance with item category N.

Regards,

Ramesh

MTerence
Active Contributor
0 Kudos

Hi Ramesh,

I did a small search in google and found this error comes for various reasons, refer below for your reference.

Google

As already suggested, MM consultants can give you the exact answers

Regards

Terence

former_member189776
Participant
0 Kudos

Hi Ramesh,

Please check below link.

https://scn.sap.com/thread/3207681

http://scn.sap.com/thread/1992003

Regards,

Ranjeet

MTerence
Active Contributor
0 Kudos

Hi Ramesh,

This can be due to Valuation Category config, Define Attribute for Material type etc.

Its good, if you contact your Materials Management consultant.

Regards

Terence