2020 Jul 17 5:12 AM - edited 2024 Feb 03 6:58 PM
In QA07 you need to specify the "initial run in days" as 1.
It won't execute that portion of the program without a value.
FYI - The blocking piece of expired batches is always done before the re-inspection, therefore expired batches never get re-inspected.
If you want to re-inspect at expiration date you can't. Not unless you have a process to keep your next inspection date in-sync with your expiration date. And then you would need to use an initial run in days for re-inspection as 2 and for expired batches as 1.