Hi Expert,

can anybody tell me

1-" why do we use network with header assignment instead of activity assignment in assembly processing"

thanx in adv

ashis

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

No it is not like that. You can use activity account assigned network also. Please refer this link. Strategy 85 is activity account assigned network. http://help.sap.com/saphelp_erp60_sp/helpdata/en/95/1613ab837b11d2b6700000e82d8bd1/content.htm

Edited by: Ahmed Rifaee on Sep 10, 2009 4:49 PM

Answers (2)

Answers (2)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Dear Ashis,


And if we at all use network with activity assignment, then cost will be collected at activity level, but we can not capture those cost, because there is no assignment of sales order with activity 

In case of activity a/c assigned network the cost is collected at the WBS to which the activity is assigned. In this case the cost doesnot roll up at Network Hdr level. An activity can be account assigned only to a WBS element. There is no way to to

account assign an activity to a Sales Order (Check assignments tab for activity).

Hence its not possible to use acty a/c assigned networks with Sales orders.

Regards

Sejo

Edited by: Sejo Srambikkal on Sep 11, 2009 11:08 AM

Former Member
0 Kudos

This message was moderated.

nitin_patoliya
Active Contributor
0 Kudos

Ashish, has correctly pointed out. Please go though this SAP Note 143545 .

Friends SAP online help is not updated. With Release 4.6C we can also use project stock in assembaly processing as well. Please go through 316434 note.

With Regards

Nitin P.

nitin_patoliya
Active Contributor
0 Kudos

This is not the ideal case. When your cost object is sales order at that time you are using header assigned network.

You cannot use activity assigned networks together with sales orders as cost objects in assembly processing. If you try to do, the system displays an error message. However you can use header assigned networks account with either the sales order or the project .

If a header assigned network is assigned to a WBS element, the system automatically assumes that the cost object is the project. In this case you cannot use account assignment category E.

For detail please find the below link.

http://help.sap.com/saphelp_erp60_sp/helpdata/EN/a5/6abf04787f11d2b6650000e82d8bd1/content.htm

With Regards

Nitin P.

Former Member
0 Kudos

This message was moderated.

nitin_patoliya
Active Contributor
0 Kudos

Ashish, Your below comment is leading to very important question.

And if we at all use network with activity assignment, then cost will be collected at activity level, but we can not capture those cost, because there is no assignment of sales order with activity .

so in this case we can't collect cost in sales order.

I am not clear on it. Requesting expert to share to share and validate us.

Ashish : Requesting you to un-answered the question, if forum allow you to do the same.

With Regards

Nitin P.