Dear Gurus
In Net requirements calculation, Safety Stock, Recipts (Purchase Orders, Production Orders, Firmed Procurement Proposals), Requirement qty(Pir, Customer requirements, Material reservations) are considerd
In My Situvation, I want to exclude considering Safety stock while doing net requirements calculation
Kindly tell me the setting i have to do
regards
palaniappan
Dear Planiappan,
In IMG Production + Material Requirements Planning + Planning + MRP Calculation + Stocks + Define Safety Stock Availability maintain 100% in AvSafetySt field. So in planning your 100 % safety stock will be considered.
Regards
Sunil Kumar