Mutiple change from REL status to TECO

Former Member
0 Kudos
1,298

Hi! PP gurus,

I have multiple RELEASED & CONFIRMED production orders, which are delivered. Now I want to do TECO because with out TECO based material is showing reflection in MD04.

Advance thanks for all helping friends.

Thanks,

Das.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Das,

If the order is delivered, that means the delivery completed tick in the order header-goods recipt tab,

Is it available in the production order? please check and come back.

Once it delivered this production order will not be available in MD04.

You can just check one production order - make it TECO manually in CO02...and check- are you getting any error...

Please come bck with answer, so that we can help you more

Former Member
0 Kudos

Dear Rajesha,

I have multiple no. of Production Order which has confirmed but not made TECO. I know to do TECO for single order. Now I am looking to do Mass processing for TECO because a huge no. of production order in system.

If any suggestion u have then pl. assist me for mass processing to make TECO.

Thanks,

Prasun

Former Member
0 Kudos

Hi,

Have you not read my previous posting in this question.

You can use tcode co44 and select complete technically

Regards,

nandha

Former Member
0 Kudos

Hi! Nandha,

I have made selection problem, after going through proper selection, that has worked. Thanks for ur reply. I will give u reward points.

Now my question is some order is showing "reprocessing record". But, I have checked that the order is not processing. Pl. explain why this message is giving?

As also, after execution of CO44/ CORM, those orders are not processing for TECO. For this reason, I am looking for answer.

Thanks,

Prasun

Former Member
0 Kudos

In COHV

Proceed as below

list = order header\

profile -std profile

selection tab

enter the plant

system status = CNF and DLV

mass processing tab

function = 220 -technically complete

no of process - maximum 99

Execute - background or online as you desaire

first - T - test run then E - Execute anc change data

Now execute

Inside the report

select all line item

menu path

Mass processing -->execute

It will give the message or log that process is done.

please come back if you need help

Former Member
0 Kudos

Hi,

You can do mass processing of production orders teco in tcode co44.

Regards,

nandha

Former Member
0 Kudos

Hi! Nandha,

I have gone through CO44, where I entered particular order no. and clicked on "completed technically", but after execution, not getting any desired result. The particular order is not transforming to TECO status from REL status.

Looking for some other answer.

Pl. suggest me.

Thanks,

Das

former_member184627
Active Contributor
0 Kudos

Hi,

You can see the production orders based on status in t.code coois.

Then you can do TECO for the orders which doesn't have TECO status

Use COHV or CORM to do TECO (for mass processing of orders)

Regards,

Senthilkumar

Former Member
0 Kudos

Hi! Senthil kumar,

I have gone through COHV and CORM, but not getting any answer.

Pl. assist any other.

Thanks,

Das