on 2009 Mar 11 2:58 AM
Dear Experts
I want to generate preventive maintenance orders for Vehicals..In this i want to take two criteria ie 2 months or 200 km.Which ever is completd first .orders will be generated and both will be started again ...
Thanks
Raj
hi
create cycle set for your requirement as months and km in IP11Z then create multiple counter plan with the created cycle set where you can specify the scheduling parameter as AND or OR type and schedule the same
regards
thyagarajan