on 2022 Nov 24 3:35 AM
Hello Experts,
We have a business requirement to setup DS scheduling in a PP-PI scenario with multiple production lines(3) for one product. Every line has a separate production version with different production times (3 PDS).Every production version (PDS) has one operation with two phases (setup and produce).
So, we are trying to use the SAP_MULT_SCH heuristic but it's not working as planned. The heuristic is not rescheduling on alternate PDS when we have multiple orders on the same day. It is not returning any error/warning messages in the log.We expect the system to automatically and evenly distribute scheduled orders across the three different production versions
The test records are as follows
一、Master Data:material no Z-FC010;Workcenter T-ZW10,T-ZW11\T-ZW12
Resource Timesteamid
PDS
二、Creat PIR,Run Heuristic SAP_PP_002 Planning of Standard Lots
Commputational ressults
Heuritic prerequiste
三、RUN Heuristic SAP_MULT_SCH
Application error, not allocated to other PDS as expected
Hi , Can i know why you have created multi activity resource ? Also as far as I know this heuristics works only with MultiMode (alternate lines using classification).If you have GR time for the products, better to review the period settings in the heuristics.
If you have a single mixed resource, alternate modes defined (using classification) and the correct periods defined in the heuristic settings this heuristics reschedules the orders correctly.
Regards
Sasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
8 | |
8 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.