The scenario is as follows: I have a production order for a configurable (MTO) material. The customer calls to cancel their order. The manufacturing is half finished (components consumed, labor posted). We sell the exact same unit to another customer under a new sales order.

Question: Can I re-assign the existing production order to the new sales order? If so, how? If not, what am I suggested by SAP to do?

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert

It is not possible to re-assign the production order to a new sales order. You should finish the production, post the goods receipt and then move the material to the new sales order stock.