on 2009 Jun 08 8:34 AM
Dear PP Gurus,
After entering the values in MS64(Copy Version) and executing the transaction following message is coming. Why requirements are not getting copied. Please guide
No. of selected reqmts 1
No. of copied requirements 0
No. of requirements not copied 1
Thanks in advance
kailash thakkar
Hi
First Check the same req is there in MD04 or not then
Try with data settings
Plant , Material no , Source version,Target version
At bottom of the screen
Do not tick - Target version active if the Target version is not 00
Do not tick - No database changes (simulation)
Tick - Create list of results
Regards
Brahmaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check whether the requirement is there in the old version or not. If no requirement is there , so it will not be there in the target version.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.