MRP Type(Time phased planning)

Former Member
0 Kudos
794

Hi all,

I am using MRP type as R1 (Time phase planning) for Finish Goods .I maintained the the following settings

MrpType R1, Planning cycle ,Planning calender , planned delivery time,Forecasting view also maintained while creating material master.

when i punch the demand in MD61 in day wise like 02/06 qty 100, 03/06 Qty 100,and i ran the MRP in MD02 i am not getting planned orders.

If any one worked on MRP type ( R1) time phased planning .please help me out

Regard

Sailendra

View Entire Topic
former_member196398
Active Contributor

Sailendra,

For Timephased Planning creation of PIR is not applicable. Please check whether you are getting any error message when you are creating PIR for this material, I am sure it should please check the log during creation of MD61.

As per this MRP procedure there is no need for creating PIR.

Regards,

Prasobh

Former Member
0 Kudos

Hi Prashob,

I agreed with you ,But how could i get plan orders. i need to create plan orders manually or what.

please suggest me.

regards

sailendra

former_member196398
Active Contributor
0 Kudos

Sailendra,

Generally all consumption based MRP types are generally used for Raw Materials. But nothing would stop you from using this for HALB or FERT materials also, for R1 MRP type based on the dependent requirement coming form header materials Planned orders would be created for this material.

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

Thanks for your prompt reply.

i need to create planned orders manually???

Regards

sailendra

former_member196398
Active Contributor
0 Kudos

Sailendra,

What is your material Final Finished Product? If so R1 MRP type is not recommended. Please use MRP type PD only, there is no point in creating planned orders manually.

Regards,

Prasobh