MRP Run

Former Member
0 Kudos

Hi All gurus,

If Production Plan is changes in between the month after execution of MRP Run or requirement of fine tuning is done as per market requirement. Here production plan is changes depend on market requirement. So how the MRP Run will take place for this requirement.

Regards,

Rajesh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi rajesh ,

ajay here , as correctly said by MR Prasobh u need to manually schedule the changed materials , to simplify the same u can create the product group for the changed material and go for MD02 with the product group name and product group Tick on the same screen.

regards

former_member196398
Active Contributor
0 Kudos

Rajesh,

In these instances you need to schedule the MRP run manually for the changed materials or for the entire plant.

Regards,

Prasobh

Former Member
0 Kudos

Hi,

Plz suggest what are the transaction means whar process step required.

Rajesh

maheshbabu_mg
Advisor
Advisor
0 Kudos

Hi Rajesh,

In transaction MDBT you can create a variant & then schedule the MRP run.

If your system is handling huge number of materials and if you are planning a Plant level MRP run, make sure you schedule the job is non-peak hours.

Thanks & regards

Mahesh

sundaresan_velayudam
Active Contributor
0 Kudos

you can change production plan by any time by using MD62

Former Member
0 Kudos

Hii rajesh!!

It depends on which strategy you are using. In material master, MRP3 view one can check the planning strategy. If we take the subjected case, strategy 40 will work fine, But, reflection of planning result will depend on your frequency of planning run. What is the frequency of your MRP run, Is it on daily, weekly or monthly basis. My guess say, it should be weekly basis.

cheers!!

kapil