MRP Run (MD01) for specific period

former_member267321
Participant
0 Kudos

Dear Friends,

I want to plan specific period sales order in MRP run (MD01). ex. System should not plan sales order having delivery date after one month.

How can i map this process in SAP?

Waiting for your reply!

Regards,

Kiran Ghule

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

As mention by Mr. Rajesha, maintain your planing horizon of 31 days and then run mrp using processing key NETPL.

Regards,

Dhaval

Answers (2)

Answers (2)

sundaresan_velayudam
Active Contributor
0 Kudos

Expert Mr Rajeesha vital is clearly explained the solution, this is the only way you can achieve your requirement

Former Member
0 Kudos

Maintain planing horizon as 31 days in OPPQ for a given plant and run MRP...