on 2006 Mar 02 10:56 AM
Dear All
Before Running MRP I have deleted all Planned Orders,
and checked in PLAF table .
Still on running MRP schedules are getting generated for deleted planned orders .
Regards & Thanks
Sushma
Dear Sushma,
From what I understand of MRP, planned orders are created based on requirements and stock levels. So, if you don't want some planned orders to be created, what you should do is delete the requirements (or increase stock level), so that MRP will not detect any need of creating new planned orders.
Hope this helps you.
Regards,
Alex