Hi Team,

While performing Subcontracting scenario, we transferred the component to the vendor against purchase order. After transfer of component the receipt element in stock requirement list of MD04 (order overview tree) Subcst (Subcontractor) is not updating. What can be the issue?

Thanks team in advance

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Do you have BOM maintained for this product and does it exploded in purchasing?

How did you perform purchase order movement type 541 was it refrence to PO?

You can monitor the stock and requirements situation with the Transaction ME2O (stock with subcontractor monitoring for the vendor).

Try to find out and eliminate the cause for inconsistencies run report RM06C020 (note 115899) using purchase order number

Best Regards,

R.Brahmankar

0 Kudos

Thanks for the revert..

BOM has maintained for the Material & same has been exploded in purchase order.

The component transferred to the vendor with 541 movement type against purchase order.

Is their any setting from MM or SD side?