MRP planning Purchase REQ per fixed lot size

Former Member
0 Kudos

Folks,

I have materials which have MRP type PD with fixed lot size of 20 pieces. Safety stock = 200 pieces. MRP run results in 10 preqs of 20 pieces each. I would like to have 1 Preq of 200 pieces. How can this be achieved?

Regards,

MdZ

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This is because of Lot size "FX" you maintained as 20.

For FX lot size system will divide the total qty as per the fixed lot qty & throw that much of PR for that stock.

So Safety stock = 200, FX =20 so PR will be 200/20 = 10 PRs

If you want 1 PR for your safety stock, then change the Lot size to "EX" then system will throw 1 PR for 200 qty as per your Safety stock

rgds

gsc

Answers (1)

Answers (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Correct.

That is due to Fix lot size.

As said by our other expert change that Fix lot size to 200.

or set minimum lot size as 200 along with maximum lot size (if required)

Regards,

Dhaval