hi all,

small question please.

we are working on 21 planning strategy. we create wbs boms. in the bill of materials we includes all materials for which mrp type may be different like PD,V1,VB. i want to know from you that, if run mrp on project base MD51, then wil mrp consider v1 and vb materials for requirement ?

or we need to run separate MRP for V1 / VB material.

pls confirm

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks for the reply

former_member196398
Active Contributor
0 Kudos

Slng,

Generally the first level components of the Order BOM would be planned, whereas if those components are having its own bom(Sub-assembly). Then it doesn't plan the second level it would just create the dependent requirement from those subassembly components. You need to preferably run either MD01 or if it is very few materials then MD03/MD02.

Hope this helps...

Regards,

Prasobh