MRP not generating proposals for dependent requirements

former_member1150623
Participant
0 Kudos
456

md05.pngmd04.png

mm03.png

Hello Experts,

I am facing an issue where MRP is not generating proposals (Planned orders) for a packaging material. Dependent requirement for future is available for the material. This packaging material is having scheduling agreement. While executing MRP for this material, a standard error occurred and which mentioned as “Maximum no. of order proposals per deadline exceeded”. Number of proposals maintained in plant parameters are 100. Planning calendar is used as PK (Friday). Minimum lot size is 0 and rounding value also set as 0. I have also searched for relevant threads throughout google, unfortunately, I don’t want to change configuration since this issue is happening for only a single material. Attached screenshot for MM03, MD04 and MD05. Material also have open contract.

Please suggest.

Thanks in advance.

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

It basically means that MRP is trying to generate too many planned orders in a single day. It usually happens when you have fixed lot sizing procedure or a maximum lot size, so MRP needs to generate too many orders in the same day.

Do you have any other setting for this material that could affect the lot size calculated by MRP? Maybe a max lot size in the quota arrangement...

Regards,

Caetano

former_member1150623
Participant
0 Kudos

Hello Caetano,

Thank you for reply.

Yes have already checked max. lot size in contract and its 12000. If checked screenshots, requirement is 1455 EA. for a single date hence logically system should create a single planned order on respective date.

Regards,

Manish