MRP Batch Job

Former Member
0 Kudos

Hi Guys:

How to setup MRP Batch Run by Buyer if we are using forecast based planning procedure?

1) Loading the Historical data into Forecasting View of the Material Master

2) MP30 Execute forecast .

3) Copy the requirements as Planned independent requirements using MD61

4) MD01 , Want to do MRP run by MRP Controller.

5) System Should Generate Purchase requistions by Buyer.

Could anyone give a detailed explanation of automating above steps since users don't have time to execute all the above steps everyday?

Can we schedule a bach job Every night for the above 5 steps?

Thanks

Sweth

Accepted Solutions (1)

Accepted Solutions (1)

sjeevan
Active Contributor
0 Kudos

RMDATIND (LSMW load of historical data from legacy system)

Historical data will build as time goes according to definitions in movement type.

Create background jobs for following using the Wizard in SM36

MD70

MPBT

MDBT (may have to define scope of planning, and I don't see any reason to run by MRP contr.)

You have the following user exit available for running MRP and I think you can make run by MRP contr. with the exit.

LMDR2001 User exits restr. profiles of opt. pur.ord.-based load bldg

LMDZU001 User exits in additional planning

Edited by: Jeevan Sagar on Oct 3, 2011 4:36 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

You need to define Batch job for the same, in that job define the steps

So that the programs will be executed one by one.

If you are not familiar with the batch job setup then take help of ABAP or BASIS