on 2007 Feb 23 12:12 PM
Hi,
Kindly suggest how to run MPS for multiple items & multi level.
regards,
Mohit
Use T-code MD41 for MPS single item multilevel but it will plans only those material which are comes under MPS and proper BOM must be defined.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
MPS run for Multiple Items can be Done using Product Group. List all the Material and Create a Product Group. Run MPS for the Product Group.
Multiple Level Run can be done only if there is Bom.
Regards,
Afzal