I have created -MOULD DIE as a PRT tool in CF01.(I dont want to create the Mould die as a Material it can only be a PRT tool)

I need to issue the Mould whenever it is required to production.

I need to have track on the PRT issued to production.

I need to issue the PRT from its storage location whenever the production requires it & track.

Keep in mind I need this Mould only as PRT TOOL (CF01).

Is this can be done ,Pls suggest a better solution.

Point will be awarded

Subbu.

Accepted Solutions (1)

Accepted Solutions (1)

madlercm
Active Contributor
0 Kudos

Hi Subbu,

You need not be concerned about defining it as a material; choose a non valuated material type. This way you skip the FI "radar"!

Then have it as a material PRT.

Then, everthing else that you need can be provided.

Regards,

Mario

0 Kudos

Thanks Mario,

1. Whether I need to maintain the PRT material in the BOM or simply I can attach in routing.

Which will have better tracebility.

2. Basically what is the diff in creating PRT as Material (MM01) and as PRT tool (CF01) (considering PM module not in the Scope).

Regards,

Subbu.

<< Moderator message - Personal information removed >>

Edited by: Rob Burbank on Oct 29, 2010 9:28 AM

madlercm
Active Contributor
0 Kudos

I think that it is just OK to attach it to the operation in the routing, but in case you actually want to issue it from stock to the order and then receive it back, I guess that you could put it in BOM too.

Material PRT has the advantage the you can track it quantity wise in stock, so you know hao many you have, where, etc..