on 2011 Mar 03 6:22 AM
Hi,
Kindly help, when my user executes KSII for month end closing, the Fixed Price OC in KSII is differ with KP27.
Please advice.
Thanks.
Mari
Request clarification before answering.
hi..
Price is calculated in Vari & fixed as per your plan in KP06. However you follow the steps to get vari & fixed price:
.KP06 1-101 Cost Centre Planning - element planning (Fixed value & Variable Value
1-102 Activity Distribution to findout Fixed/Variable Price
if both are required paln Variable quanty
otherwise Fixed qty
KP26 1-201 Activity Planning (Activity qty)
Pl revert back if your issue is resolved.
kkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi..
T.code KSBT
kkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When i went to Tcode: KSBT to check, there are some cost fall under Fixed Price in OC and some fall under Varible Price in OC,depend on the Activity Type. Ex. Electricity is under Var Price OC, and Operation Cost is under Fixed Price OC.
However, in KSII, all of the price is allocated in Fixed Price OC only.
Can you please advice what shoud i do to get the correct price in KSII.
Thanks.
Mari
hi..
Your question is something confusing.
KSII is for actual price and KP27 is for plan price.
You goto KSBT and see the price for Actual select price indicator 5 and for plan 1 or both at a time.
kkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
39 | |
8 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.