Hi gurusm

¿Is it posible to modify unit of measure of a material in a purchase order if a partial quantity is entried in MIGO? When you do MIGO, in purchase order, field for unit of measure is not editable.

Thank you,

I will revvard answers!!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

After GR you cant modify the UOM. It is not possible.

Former Member
0 Kudos

In SAP nothing is imposible :p.... it's a joke..

Former Member
0 Kudos

Hi Daniel,

Its a fact or a joke,what ever you think.

Either post the remaining GR and cancel the relevant documents.

Change the UOM, change it in material master.

Give your alternate UOM and save.

Regards,

Nani

JL23
Active Contributor
0 Kudos

reduce the order quantity of your PO item to meet the already entered partial receipt.

Create a new item with the new unit in your PO for the remaining quantity

Answers (1)

Answers (1)

Former Member
0 Kudos

I think that provision is not feasible,so do the GR for full qty or cancel the existing GR and cancel the PO and maintain the alternate UOM in Material master then do a PO and GR