Dear experts,

We have done some testing regarding the ML Activation with valuation at company level. To our understanding, the ML can't be activated with material valuation at company code level (the ML active indicator in the material master can't be activated), and to my understanding, cost estimate can't be created at this level of valuation, thus meaning that actual cost component split activation is not possible also.

Are we missing something here?

Please kindly suggest

Thank you very much in advance

Best Regards,
Erwin Hartono

Accepted Solutions (1)

Accepted Solutions (1)

marialuisa_munoz
Contributor
0 Kudos

Hi,

Yes exactly. Almost all of our customers work with plant level for the reason that
some functionality are not available with company code level.

Please read documentation for customizing transaction OX14.
It says: " Plant level Valuation must be at this level in the following cases:

- If you want to use the application component Production Planning (PP) or Costing "

For the material cost estimate as well as for order costing or network
costing, the valuation can only be executed on plant level. Please have a look at the attached note 171244.

I hope this helps.

Best regards,

MLM

Former Member
0 Kudos

Hi,

Thank you for your answer.

Best Regards,

Erwin