on 2007 Jul 31 9:05 PM
hi pp experts,
please tell me about mixed mrp and where it is used .
thanks in advance.
nr
Hi,
Mixe Mrp indicator is an indicator which is used for spl purpose planning
For ex in strategy 11
In this strategy the plant stock is not taken into account
For ex in strategy 59
In this strategy dependent reqmts are created for the components
of the phantom assembly skipping phantom assembly ,planned orders and purchase requisitions are created for the components
For ex in strategy 70 and 74
PIR'S are created at assembly level and sales order at fert level
Hope this will help in understanding about the Mixed MRP indicator.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,thanks for ur reply.
nr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Narotham,
Above one gives you clear picture about it , you should give him full point and close the issue
Thanks
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.