Missing WIP calculation in prev period

former_member504485
Participant
0 Kudos
195

Hi

I have a problem with production orders, to which some goods have been issued in eg. period 11, but the confirmation (CNF) is made in period 12 (01.12.2013). When I execute the WIP calculation in new period (02.12.2013), I do not get any WIP numbers end of period 11... I believe it is due to that the order got status CNF in current period when the WIP job is executed.

How to solve this issue - am I able only to include 'status' for the single production order up to a WIP period so status changes in new period is not taken into account when the WIP is executed in period 11?

Thank you in advance.

BR

Søren

View Entire Topic
Former Member
0 Kudos

Hi,

Please check "Cut off Period" txn.KKA0.

Thanks,

Szymon

former_member504485
Participant
0 Kudos

Hi Szymon

Thank you for your reply.

From my perspective this issue has nothing to do with CutOff period, due my problem is that no WIP is calculated when order has status CNF even though it is in a period later than the one I run the WIP.

.

BR