Hello All,

We are facing the following problem with Migration Cockpit. When we are migrate material master data, all steps is working fine, and quite fast, but the migration step is always runnig for 25 minutes.

It worked fine before, only took 1-2 minutes to finish the migration step as well.

Have you faced any similar, or how, where this 25 minutes is set in the system?

S4HANA ON PREMISE SAP S/4HANA 2021 01 (02/2022) FP

Thank you

Regards

Szabina

View Entire Topic
Stephen_Zhang
Advisor
Advisor

Hi,

Good day.

You can check if all the latest corrections have been applied to your system. You can use the report “Analyze SAP Notes” (CNV_NOTE_ANALYZER_MC_EXT). Kindly Re-implement SAP note 3016862 - Note Analyzers with separated scenarios for ABAP-based Migration and Replication Technology (DMIS2011/DMIS2018/DMIS2020/SAP S/4HANA) - Note Analyzer .

This will help to examine if you have all the latest Migration cockpit corrections and rule out if this issue is being caused by not having the latest corrections.

For reference see - https://blogs.sap.com/2020/05/28/how-to-implement-the-latest-corrections-released-for-migration-cock...

Best Regards,