on 2008 Dec 30 8:55 AM
Hi Experts,
Can we make control on material type such that after posting of MIGO(101) material should not come on stock it should directly go to consumption account. Plz explain.
Thankl you
Sap MM
pending
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go in Material type setting.
Enter OMS2 - Material type.
Select your material type, Click on By valuation are in Quantity updating & In no valuation area in Value updating in the tab of Quantity/Value updating options.
Regards,
Mahesh Wagh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
u have to maintain the material as NLAG(the material NLAG stands for nonstock material.neither quanity nor value is updated for this type of material in stock.these material are only procured with account assignment).
you will not do this in MIGO, you have to do this in the purchase order already.
u have to mainta an account assignment in purchase order, then the goods receipt will post to consumption instead to stock
hope it solves ur problem
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go thro' PO Direct posting process means using Account assignment (k-cost center,n-network ,P-project) Wirh G/L account assignment
transaction code ME21N
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you dont do this decision in MIGO, you have to do this in the purchase order already.
If the purchase order has an account assignment, then the goods receipt will post to consumption instead to stock.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
select non stock material
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alwyn,
Go to OMS2 transction select the material type and go to Quantity/value updation click on this field and the check box ,remove if it is in Quantity update . You can controle the the materials created under material can be make as non inventorised.
I hope it will help ful for you...
Thanks and regards.
R.R.Rao