Hi Experts,
I have created a general tasklist with 10 operations. Assigned equipment in each operation. Selected the operation and also assigned measuring point as PRT. Created a new maintenance order and assigned the tasklist to the order. System automatically copies operation/prt from tasklist to the maintenance order.
Release the order and saved.
Now I opened IW41 and entered the order number and operation number. Screen opens to enter the confirmation details. In the top, I have a icon "Measuring Document", I clicked the icon to enter the measuring document for the measuring point assigned in the operation. But I couldn't see the measuring point. System expects the user to manually assign the measuring point again in the confirmation screen.
What is the use of assigning the measuring point in the operationa as PRT?
Am I missing any configuration setting to system automatically pick the measuring point from the operation I have assigned already.
Hi Team,
I got the solution. IW42
Click Extras --> Settings.
Select the profile maintained in customizing.
std dropdown is 1,2,3.
Once I selected this, I am able to see the "Measu point Inspection Planning" button.
Click this button, system automatically picks all the measuring point assigned as PRT in maintenance order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
7 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.