on 2011 Dec 16 9:03 AM
How a Measurement document and Maintenance Order can be connected.
1. While processing a Maintenance Order, a Measurement document can be updated.
2. While processing a Measurement document, Maintenance Order can be created.
Please suggest.
Hi Raja,
Your Question
1. While processing a Maintenance Order, a Measurement document can be updated.
Yes you can surely update the measuring document with the maintenance Order, you can do the same at the time of confirmation of the operations.
2. While processing a Measurement document, Maintenance Order can be created?
Yes you can definitely achieve the same via User Exit Given by SAP for the generating of the maintenance Document(Notification or Order), if the Measuring point reading lies outside the upper and lower limit.
Hope it helps you.
Regards,
Yawar Khan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Reference order number will be updated in IK17 report.you can able to track
if you see in IK13, Reference order will be there.
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
8 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.