ME84/ Scheduling Agreement via Idoc / E1EDP10-MFADT isn't filled

Former Member
0 Kudos

Hello,

I have a problem with the content of the field MFADT(Cumulative production go-ahead quantity requirements) of the segment type E1EDP10, when I create

the SA Releases via Idoc with ME84. It is empty.

In my scheduling agreement in tne section 'Scheduling control' the Firm Zone is equal 14 days. And in my Idoc I recieve the right  content for the field E1EDP10-ABFDE(End of production go-ahead) = today + 14 days. In my delivery schedule I have requirements within this period. All this reqirements I can see in my Idoc with the correct quantity. All other information in the Idoc is also correct, except of the cumulative quantity requirements for the go-ahead-period. Please advise, what is the system expecting to get this information. Thanks.

Olga

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Olga

I also looking for an answer to fill the fields MFADT and MFRFZ in the segment of E1EDP10.

What i found is always pointing to APO or SCM nowadays.

Really appreciate an answer bringing in some lights into the darkness.

See here