on 2011 Aug 05 7:30 AM
Dear Experts,
I have done total of PO list from ME2j report & it was around 9267023.55.
But, when i check S_Alr_87013558 assigned amount, its showing 8,518,082.39. Also at same time i have observed that Gl codes in PR & PO was different.
Why ME2j total is greater than assigned amount? It should be less than ME2J or same.
Please help.
Thanks & Regards,
arvind Tirloktar
arvind,
it generally happens,please check whether availability control is active or not. if not then please activate .or check through ststus management that may be availabilty control ihas been deactivated for few time and entries passes in between that time.
bibhash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bibhaskumar,
Thanks for your reply.
I have checked Availability control, it was active only once before creating PR & PO.
I have only quiestion that, why ME2J total is greater than Assign amount of Cj30 or S_ALR_87013558.
If availability control was inactive then assign amount was also increased in CJ30.
Please help.
Thanks & Regards,
Arvind Tirlotkar
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
115 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.