MD04 Display error(planned order id displaying first then dependent reqmnt.

former_member1242643
Participant
0 Kudos

Hi Gurus,

After MRP run for a material ( there is a dependent requirement for the material), when i am displying MD04, i am getting the planned order first(with corresponding available stock) and then in the next line dependent requirement(with available stock 0).

But actually it should show dep. requirement first and then the planned order.

Can you please tell how can i get the screen(MD04) properly? is there any settings for this? i am getting this only for one material.

Regards

Rajib Pathak

Accepted Solutions (0)

Answers (1)

Answers (1)

Anupam1143
Active Contributor
0 Kudos

HI

Check the date of both Dep Requ and aplanned order.also check the startgey for both dep and PIRs

If they are different then they will show separately

check and revert

Regards

Anupam Sharma