In our process we analyze the MCPS result to have some information system about result production in a certain periodo entry.

In this analyze is knowledge that when the orders are complete confirmed or defined status TECO the information of production order as process duration, time confirmed are all with value zero. This behavior seems be standard by SAP.

Anybody has idea about any solution to MCPS ?

Or a specific report that same after confirmed the order or with status TECO will be possible to have the original information about the quantities, time schedulled or time confirmed  by the production order?

Is possible to change this behavior ? at the production order or  MCPS / LIS tables?

Best & Regards

BR

Itamar do Prado

Accepted Solutions (0)

Answers (2)

Answers (2)

solomon_macwan
Active Contributor
0 Kudos

hi Itamar,

Apart from Caetano has answered the thread, I would like to add that, when you click on the information button it will show you the info structure name.

you open that table S022 and you can see some primary keys. now any change in the primary key will add a new line into the info structure.

for example date or time or version as Caetano has said. so once the information is fetched for at the time of release it will not come again when you do the teco.

regards,

Solomon

itamar_doprado
Explorer
0 Kudos

Hi

Thanks for the help,

I understood about the version actived on the OPL5 to take  a information on the LIS tables or (MCPS), but in cases where I released the order with a quantity of 1 UN and after it will be change to 2 UN, the version created before would be updated to 2UN on the  MCPS?

It will be update in cases of changes, or not?

Regards

Itamar

itamar_doprado
Explorer
0 Kudos

Guys

Anymore has idea about the last doubts?

Thanks

Itamar

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

On transaction OPL5 you can define that the "release version" will be stored for an info structure.

The release version is the version at the time of the release, it means that the values on the infostructure are the values of the order when it was released. Therefore, subsequent changes in the order are not considered.


BR

Caetano