Hi,

Against production order reservation number we are doing goods issue in MB26. We do GI for few components and the remaining later. I posted say 10 out of 25 components, when i try to post the remaining components (15) against the same reservation number, i am getting the error message " no goods movement can be selected".

Cross checked the production order. for the issued materials final issue is checked.

Still for the remaining components, the quantity are open. could anyone suggest how to approach for this issue?

Accepted Solutions (1)

Accepted Solutions (1)

former_member311826
Active Contributor
0 Kudos

The material with backflush tick does not comes in Picklist report. This material will get issue when you do the confirmation. Click on Goods movement screen in confirmation scree you will see all this 10 materials there. If you want to issue this material through Pick list you have to remove the Backflush Indicator. Remove it from Production Order & then check MB26

Former Member
0 Kudos

Thanks. For SFG, issue solution as mentioned by you.

for raw materials, user posted with the proposed quantity, so system was not picking the reservation.