Former Member
0 Kudos

Hi ,

as soon we create production order rev of component are done by the system against the particular prod order, now problem is suppose compo A having stock of 100 EA, for production 50 EA is reserved now the free stock is 50 EA ,now i am issuing compo to other material qty of 100 EA , IT IS ALLOWING ME , if the remaining quan is 50 Ea , how it is allowing me to issue 100 Ea, is there any setting to prevent issue ,

Regards,

vikas

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vikas,

Check this Message no 362 for Message class M7 in OMCQ transaction.

While issuing the 100 qty check whether the system is throwing any warning message like M7 362.

If not goto

spro-mminventory-system attributes and messages- select message settings

or goto direct transaction OMCQ include this Message number 362 for M7 message class.

and made it as error message.

Check if still it allows to issue let us check other options.

rgds

Chidanand

Former Member
0 Kudos

Hi,

my problem is like this total qty is 100 cv, out of this 50 cv is reserved for particular prod. order, now balance qty is 50 cv, if i am doing MB1A for this material it should not take reserved qty , it can take upto 50 cv,

vikas

Former Member
0 Kudos

M7 362

Go to OMCQ

Replace this message From W to E

Former Member
0 Kudos

Hi Guru,

Can OMCP solve my problem?

Pl suggest.

Vikas

Former Member
0 Kudos

while issue of this material more than 50 for other use, system must be giving warning message.

Make it as a error.

Former Member
0 Kudos

how we can do?

pl explain.

Vikas

Former Member
0 Kudos

Note the message no. & class while issuing material to another use .

Then go to OMCQ

Find this class & mes no. Make it as E