Dear All,

We are having the scenario that every month updating the material price (MR21) and system creates two accounting documents

Dr Finished Goods GL

Cr Cost of Prodn GL

Dr Cost of Prodn GL

Cr Finished Goods GL

Sometime back we missed out to execute the price change process during 2018 and still the system keeps the same standard price for the material what was available.

Even we change the material price change (MR21) now also, but the system keeps still the same price.

Now we need to get it back the earlier stage as that the system should post two price changing document and old value should be 0

Regards

material-price-information.png,

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Go to OMRN and see whether the box "Price carry over" is ticked for the company code. If not, take the concurrence from Business Finance team and if they are okay, tick that box and test it.