Material Determination through INBOUND IDOC

Former Member
0 Kudos

Hi Experts,

I have a senario like i need to update the material determination tables when i receive an in bound idoc to create a material. (msg type : MATMAS , Basic type: MATMAS05, Process code: MATM). But i have not seen any segment in the BAsic type to do tht and also there are no user exits for using call transaction after the material creation in the Process code FM. Do u know any BADI or FM can do this. Rewarded with points.

Thanks,

Naren.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

following are the segments in the Basic Idoc type MATMAS05

E1MARAM Master material general data (MARA)

E1MARA1 Additional Fields for E1MARAM

E1MAKTM Master material short texts (MAKT)

E1MARCM Master material C segment (MARC)

E1MARMM Master material units of measure (MARM)

E1MBEWM Master material material valuation (MBEW)

E1MLGNM Master material material data per warehouse number (MLGN)

E1MVKEM Master material sales data (MVKE)

E1MLANM Master material tax classification (MLAN)

E1MTXHM Master material long text header

E1CUCFG CU: Configuration data

and you search for the CUSTOMER-FUNCTION in the Function module attached to the process code forwriting the User exit part.

Reward points if useful

Regards

Anji

Former Member
0 Kudos

Hi Anji Reddy,

I kniow the IDOC structure and how to find the user-exits but there is no user exit in the process code FM just after creating the material. I need any update FM for tht to use before the material creation.