Dear Experts,

An Assembly material can be dependent requirement for a Higher level material ( In case of MTO) ,  and can be planned through Planned Independent Requirement. (PIR)

There is two plants, One is planning Plant (1100) and other is production plant of that assembly (1200)

In MTO, Planning plant is used for Sale order Delivery/Shipment i.e. 1100 plant is given in VA01 for line item of Higher - Main Material  ( Sales order creation )

Assembly Material is extended on both Plants views, On both Plants View, What planning strategy should be used ?

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

In this scenario you need to have MTS +MTO planning strategy.

Refer this document on it,

Best Regards,

R.Brahmankar

ahmed_sappp
Explorer
0 Kudos

Dear Rupesh,

Thanks for your reply.

Material is extended on both plants view i.e. 1100 & 1200

Please specify MRP Views settings ( Specially Planning Strategy Group ) on both plants views ! what ll be entries in both plants view?

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

You can use the special procurement key production in alternative plant. Please search in this forum you will get lot of discussion on it.

Refer SAP help  documnet on it

Production in Alternative Plant - Special Planning Processes - SAP Library

Best Regards,