Dear Pal

Pls clear the scanario for the below which you are following.

1. In mtc order first we are monitoring the materail cost +consumtion. If user gets the same thro 201 movement they are not creating the mtc orders for reservation.

But some general work mtc & material what will be the best

We are following the restriction of this movement. Pls tell me what abt your case & idea

Pls tell me how to change the reservation date after creation? because some times they are taking the materail for orders after 1 month period which is not advisable.

View Entire Topic
former_member187991
Active Contributor
0 Kudos

hi

If you are doing maintennance activity then it is better if you create an reservation through order it will have a better control through maintenance order itself. if you want to change the material reservation date created through maintenance order then in the order schedulling parameters make the settings as adjsut basic dates to operation dept requirments,then as you change the operation date it will reflect for the reservation also