on 2019 Mar 26 7:05 AM
We are using Production Version, BOM (using tcode CS01) and Master Recipe(using tcode C201) standard for a product code. We are a pharmaceutical industry and so we are creating Process Order (using COR1).
When we generate Process Order (using COR1), system ask for Order Quantity then we enter Order quantity same as we maintained BOM and Recipe standard. Normally our standard batch size is fixed means for which quantity we maintain BOM and Recipe standard similarly we create Process Order for same batch size (order quantity).
But in some case we need to change order quantity at the time of process order creation. In this scenario, suppose a BOM and Recipe standard quantity is 100 units and we create process order for 50 units then system auto calculate BOM components quantities but the issue is that system is not auto calculating standard hours of Master Recipe.
I want to know how system will auto update standard hours of Recipe as it calculates BOM components depends on order quantity.
for example:
Standard BOM Batch Size is 100 unit and Standard component quantity is 10 unit
Standard Recipe Batch Size is 100 untis and Stanadard Activity hours is 10 HR.
IF WE GENERATE PROCESS ORDER and enter Order quantity 50 units.
then system calculates BOM component quantity is 5 units
But do not update Activity hour it remains same which is 10 HR.
Regards,
SZ
Can you describe me an example from where i can define formula and how?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I didn't find activity values and resource formula from where i can check fixed value option.
But I did the same procedure and press F8 at material tab and then check operation standard values but it remains same. Also i noticed that Operation quantity is updated but base quantity as per standard although i have changed order quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, found option in phase detail , material components tab.
But here it is used to calculate quantity not standard hours if i am not wrong.
please guide.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check the master recipe for activity values and resource formula if it is based in fixed values.
Operation quantities can be calculated with the formula maintenance in the material quantity calculation.
In process order go to the materials tab and perform the material quantity calculation and you press F8 to copy the results. Now you go to the operations tab and select a phase and go to the details view of the selected phase. Here in the Standard Vals tab you find that the operation quantity is updated.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear R Brahmankar
Need your help, please
https://answers.sap.com/questions/13774124/automatically-show-the-activities-value-as-per-rec.html
Thanks
M.G Rabbani
Hi Shahab,
Please check Resource (work center) formula
And also Check is there was MQC at operation or NO?
Regards,
Muhamed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muhamed
can you help me,,,Please
https://answers.sap.com/questions/13774124/automatically-show-the-activities-value-as-per-rec.html
User | Count |
---|---|
102 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.