Hi experts,

Please help me to solve this case:

I have a planned order and want to convert it into process order, this message appears:

No task list within validity period of production version

Message no. CP006

Diagnosis

During routing selection, the system searches for production version . A routing exists for this production version, however, it is not valid for the validity period of the production version.

I checked and found that the validity period of master recipe & production version are the same.

Using COR1, I can create process order with appropriate Master Recipe!

All settings for master recipe selection in COR4 are correct.

What seem to be the problem here?

View Entire Topic
Former Member
0 Kudos

Hi,

Check the Production version validity and also the lot size .

Order Qty must be with in the lotsize range.

Hope this clears you.

Thank you.

Naveen.

Former Member
0 Kudos

Hi Alapati,

Thank you for your answer. Before posting this question, I also found that order quantity lay outside Lot Size range of production version, but I didn't think that's the cause as the message does not relates to quantity at all. Your answer pushed me to try, and it's solved!

Cheers,

Duc PB

Former Member
0 Kudos

Hi Naveen,

Thank you for your answer. Before posting this question, I also found that order quantity lay outside Lot Size range of production version, but I didn't think that's the cause as the message does not relates to quantity at all. Your answer pushed me to try, and it's solved!

Cheers,

Duc PB