Mass close production orders

SAPSupport
Employee
Employee
0 Kudos
133

How to change production order status to closed automatically once the production order status changes to Finished. 


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.
View Entire Topic
SAPSupport
Employee
Employee
0 Kudos

When a production order is released, a production lot is created. The planned structure (operations, activities, and reporting points) and the planned data of the production order are copied to the production lot and used as a basis for creating production tasks and default values. 

When the production tasks and, consequently, the production lot are finished, the production order is automatically finished. 

When the production lot is closed, the production order is automatically closed as well. 

Depend on above, you can create a Lot Closure Run to close the mass production lot automatically and ,consequently, the production orders will automatically closed.

Please refer to the documentation for more information. https://help.sap.com/docs/SAP_BUSINESS_BYDESIGN/2754875d2d2a403f95e58a41a9c7d6de/2ddeccfe722d101494c...

 

Create a Lot Closure Run steps:
  1. Choose the Lot Closure Run subview.

  2. Click New to open the New Automated Lot Closure Run quick activity.

  3. On the General Data view, enter an ID and a description for the run.

  4. Specify further selection criteria for the run using the tabs available. The system automatically includes or excludes production orders based on these criteria. In the lower table, on each tab page, click Add Row to add a new row.

    • Filter production lots using a selection range

      In the Inclusion/Exclusion field, click the arrow and choose Inclusion or Exclusion. In the Search Pattern field, click the arrow and choose Equals. In the From and To fields, select the start and end range for selection.

    • Filter production lots with reference to a particular selection

      In the Inclusion/Exclusion field, click the arrow and choose Inclusion or Exclusion. In the Search Pattern field, click the arrow and choose the appropriate operator, for example Less than or Equal To. In the From field, select the business document for the selection, for example Product ID 8186.

    Repeat the steps outlined above to specify the selection criteria for each relevant tab.

  5. At the top of the New Automated Lot Closure Run quick activity, click Save. Then click Close to return to the Automated Actions view.

    Note

    You can choose to activate the run from here, or you can activate the run later, just before scheduling. Click Set to Active to activate the run from here. To activate the run later, select the run you want to activate. Click Actions and then choose Set to Active.

    The new lot closure run has been created and saved to the system. You can now define a schedule for this run.