Mass ATP Check

Former Member
0 Kudos

Hi All,

In the transaction of mass processing for process order - COHVPI we have checked the indicator for 'Reset availability data'. Thus system will first reset the availability data & then do the availavility check again for all the process orders.

My query is that in what sequence will the system do the availability check for the process orders again - is it is done in sequence of process orders by its numbering or by the requirement date of the components or by any other factor.

regards,

Mohit

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

The orders are checked in the sequence in which they are displayed in the object detail list (i.e. the top order is checked first). You can change the sequence using the grouping and sort functions of the production order information system.

Regards

Brahmaji